Project Scheduling

  • b00130630
  • Nov 7, 2021
  • 3 min read

Updated: Nov 30, 2021



ree

Figure 1: Project Schedule on MS Office


This blog examines project scheduling and the relationship between different tasks within the project.


The schedule is the conversion of a project action plan into an operating timetable. It is a monitoring and controlling aid for the entire project.


A schedule can be displayed as network of activity and event relationships between all the various inputs, known as a network diagram (See Figure 1). Tasks that must precede or follow other tasks are then clearly identified as are the dependencies between different tasks. This shows how the tasks will affect the overall project duration is delayed.


The two most common networking techniques are PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method). The techniques two are quite similar and are interchangeable.



Terminology


Here are some terms used in project scheduling:


  • Activity: A specific task or set of tasks required by the project.

  • Event : The result of completing an activity. It is an end state occurring at a particular time and uses no resources.

  • Network: The combination of all activities and events that define the project and the activity precedence relationships.

  • Path: The series of connected activities (or intermediate events) between any two events in a network.

  • Critical: Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is the sequence of critical activities that connect the project’s start event to its finish event.


An activity may have a successor, but no predecessor, in which case it starts a network. It may have a predecessor, but no successor, in which case it ends a network. Or it may have both predecessors and successors in which case it is in the middle of a network.




ree


Figure 2: Activity on Node and Activity on Arrow


There are two main networks used to display activities (See Figure 2):


  • Activity on Nodes (AON): networks use nodes to represent activities with arrows to show precedence relationships

  • Activity on Arrow (AOA): networks use arrows to represent activities while nodes/boxes stand for events


The AON networks are easier to draw and they are the type used in MS Project.


Each node on the Gantt Chart includes certain additional information required for that node such as activity name, the duration, the Earliest Start Time (EST), Earliest Finish Time (EFT), Latest Start Time (LST) and Latest Finish Time (LFT).




ree

Figure 3: Critical Path Method


Critical Path Method

The critical path for a project is the series of activities that determines the earliest time by which the project can be completed. The Critical Path Method is a network analysis technique used to predict total project duration. A critical path for a project is the longest path through the network diagram and has the least amount of float. The critical path in Figure 5, is the path outlined in red and this project is scheduled to take 54 days to complete. A good project network diagram will help to develop a more accurate critical path.


ree

Figure 4: Forward and Backward Pass Calculation


Forward Pass Critical Path


To calculate the Earliest Start Time for an activity, sum the durations of the predecessor tasks. To calculate the Earliest Finish Time, add the duration of the activity to the Earliest Start Time. Do this for all tasks to estimate the Earliest Finish Time for the Project. The longest time path is the critical path. This is called the forward pass method to establish the critical path method and it moves from left to right across the network diagram.



ree

Figure 5: A Different Kind of Backward Pass


Backward Pass


The backward pass is a method to ensure deadlines are met. It calculates the latest start time and latest finish time for each activity within the critical path, starting with the finishing time for a task and subtracting the duration. This identifies if there is 'slack' time for any task and lets the project manager know if resources should be reallocated.





 
 
 

2 Comments


b00123411
Dec 24, 2021

Hi Elaine! You explain a difficult topic very clearly and you make it easy to understand. Good work! Michaela

Like

b00123810
Dec 09, 2021

Really good blog, great use of visual aids to assist with understanding the topic, well done! Kerry

Like
Post: Blog2_Post
  • Facebook
  • Twitter
  • LinkedIn

©2021 by Project Management Dublin. Proudly created with Wix.com

bottom of page